Back to index Original on gov.scot

FOI/202300367798 · FOI · unclear

Communication between Scottish Government and SSEN: FOI release

Published
2023-08-21
Received
2023-07-20
Responded
2023-08-11
Directorate
Energy and Climate Change Directorate
Topic
Environment and climate change, Public sector
Exemptions
None detected

Information requested

The date that SSEN first informed the Scottish Government of their proposals to create a transmission corridor between Kintore and Tealing.

Response

The answer to your question is SSEN first informed the Scottish Government of their proposal to create a transmission corridor between Kintore and Tealing on 20 January 2023. This was received via a completed pre-application form emailed from SSEN to the Energy Consents Unit. About FOI The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

Contact Please quote the FOI reference Central Enquiry Unit Email: ceu@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrews House Regent Road Edinburgh EH1 3DG

Attachments

No attachments found.

Similar releases