Costs of National Care Service - planning and implementation: FOI release

Published
2024-10-09
Received
2024-08-29
Responded
2024-09-20
Directorate
Health and Social Care Finance Directorate
Topic
Health and social care, Public sector
Exemptions
None detected

Information requested

Could you supply the full costs to the Scottish Government of planning and implementing the National Care Service scheme, with a breakdown per year and what the money was spent on?

Response

Please find below a breakdown of the high level costs of the NCS since it's inception in 2021/22.

These costs have been taken from the financial ledger. (Note - in 2023/24 the sub ledger codes for Co-Design and Grant Funding were added to provide additional detail).

2021/22 2022/23 2023/24 2024/25 P01-05 Cost Area (£k) (£k) (£k) (£k) Staffing Total Staffing £1,387 £9,800 £9,823 £3,374 Non Staffing Co-Design £104 £9 Engagement £66 £1,026 £17 £6 Grants £359 £131 Research & External Support £302 £1,683 £355 £12 Staff Related £31 £134 £87 £29 Total Non-Staffing £399 £2,843 £921 £187 NCS Total £1,785 £12,643 £10,744 £3,561

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

Contact Please quote the FOI reference Central Correspondence Unit Email: contactus@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrews House Regent Road Edinburgh EH1 3DG

Attachments

No attachments found.

Similar releases