Strategic Transport Projects Review 2 costs: FOI release
Information requested
The total cost to produce the Strategic Transport Projects Review 2.
Response
The total cost of the second Strategic Transport Projects Review, undertaken between February 2019 and December 2022, is £10,201,132. It should be noted that the STPR2 Delivery Plan which is now underway is out with the scope of this request.
About FOI
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.
Contact Please quote the FOI reference Central Enquiry Unit Email: ceu@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrews House Regent Road Edinburgh EH1 3DG