The number of subsea fibre cables that have been laid in Scotland and in Scottish waters: FOI release
Information requested
How many subsea fibre cables have been laid in Scotland and in Scottish waters in the period 1 September 2021 to the present day. Please if possible include Scottish Government funded cables that have been laid and also those laid with private sector funding.
Response
I enclose a copy of some of the information you requested.
In the period 1 September 2021 to 1 August 2022, 12 of a total of 16 planned subsea cables have been laid as part of the Scottish Government funded Reaching 100% (R100) programme.
The laying of the R100 subsea cables started in May 2022 with work ongoing to lay the remaining cables. The routes for the laid subsea cables are:
Yell to Unst Shetland to Yell Shetland to Whalsay Fair Isle to Shetland Sanday to Fair Isle Sanday to Stronsay Eday to Westray Eday to Sanday Orkney to Shapinsay Hoy to Flotta Flotta to South Ronaldsay Eigg to Scottish Mainland
The routes for the 4 remaining subsea cables due to be laid this year are:
Colonsay to Mull Scottish Mainland to Lismore Iona to Mull Orkney to Rousay
Further information regarding these subsea cables can be found on the R100 website: https://www.scotlandsuperfast.com/the-r100-programme/r100-subsea-deployment/
With regards to subsea cables laid with private sector funding, we can only provide data pertaining to subsea cables laid through the Scottish Government’s Reaching 100% (R100) programme. Any cables laid through private funding is considered commercial data and not something we hold.
About FOI
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.
Contact Please quote the FOI reference Central Enquiry Unit Email: ceu@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrews House Regent Road Edinburgh EH1 3DG
Attachments
No attachments found.