Back to index Original on gov.scot

FOI/202100165980 · FOI · unclear

Domestic Electric Vehicle Charging Point (EVCP) in local council area: FOI release

Published
2021-04-14
Received
2021-02-22
Responded
2021-03-15
Directorate
Topic
Communities and third sector, Public sector, Transport
Exemptions
None detected

Information requested

How many EVCP units have been grant funded in Fife? What is the nature of these units that have been funded eg domestic, public?

Response

As at end December 2020, the number of EV chargers that have been grant funded in Fife were as follows:

Public EV chargers - 72 Domestic EV chargers - 651

About FOI The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

Contact Please quote the FOI reference Central Enquiry Unit Email: ceu@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrews House Regent Road Edinburgh EH1 3DG