Back to index Original on gov.scot

EIR/202500458982 · FOI/EIR · unclear

Statistics on solar panels installed across Scottish Government estate: EIR release

Published
2025-06-26
Received
2025-03-25
Responded
2025-04-16
Directorate
Scottish Procurement and Property Directorate
Topic
Energy, Public sector
Exemptions
None detected

Information requested

How many Scottish Government buildings have installed solar panels on part of the building? Please provide detail on how many panels exactly, how much energy they produce etc. Please provide as much detail as possible on how these panels were procured. From what company, how were they produced, how much did they cost in total etc.

Response

6 buildings on the core Scottish Government estate have solar panels installed.

Building No. of panels Kilowatts peak (kWp) Annual average kWh Cost SASA, Edinburgh 560 153 142,588 £243,370 Victoria Quay, Edinburgh 318 95.5 86,669 £305,237 St Andrews House, Edinburgh 110 47 37,211 £122,996 Cameron House, Oban 114 32.49 25,518 £14,470 Thainstone Court, Inverurie 54 20.52 18,816 £24,712 Tweedbank, Galashiels 27 10.26 9,821 £13,712

The panels were procured following competitive tender exercises in line with Scottish Government procurement rules. The tenders were carried out, and projects delivered by the Scottish Government's facilities management company Mitie.

The panels were produced by JA Solar for Tweedbank, Oban and Thainstone. The panels at Victoria Quay were produced by Solar World AG. The panels at SASA and St Andrews House were produced by Hanwha Q.CELLS

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at https://www.gov.scot/foi-responses.

Contact Please quote the FOI reference Central Correspondence Unit Email: contactus@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrew's House Regent Road Edinburgh EH1 3DG