FOI/202500451670 · FOI · not held

Bus replacement scheme funding: FOI release

Published
2025-03-19
Received
2025-02-06
Responded
2025-03-06
Directorate
Topic
Public sector, Transport
Exemptions
17(1)

Information requested

1. Detailed breakdown of the funding allocated for the RAIB bus replacement scheme from East Kilbride to Glasgow Central.

2. Confirmation of whether the costs associated with the bus replacement scheme have been included in the overall funding for transportation projects by the Scottish Government.

3. Any correspondence or documentation related to the approval and funding of the RAIB bus replacement scheme.

Response

For points 1 and 3 of your request

Whilst our aim is to provide information whenever possible, in this instance the Scottish Government does not hold the information you have requested. This is because the alternative transport plan, which has been put in place for the duration of the necessary improvement works on the East Kilbride to Glasgow line is being managed by ScotRail.

This is a formal notice under section 17(1) of FOISA that the Scottish Government does not have the information you have requested.

For point 2 of your request

We can confirm that an estimated cost of providing alternative passenger transport has been included, by Network Rail, in the Anticipated Final Cost for delivering this project on behalf of Transport Scotland.

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at https://www.gov.scot/foi-responses.

Contact Please quote the FOI reference Central Correspondence Unit Email: contactus@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrew's House Regent Road Edinburgh EH1 3DG