EIR/202400404912 · FOI/EIR · unclear

Ferries built by Ferguson Marine for Caledonian MacBrayne: EIR release

Published
2024-09-04
Received
2024-03-18
Responded
2024-04-15
Directorate
Economic Development Directorate
Topic
Economy, Public sector, Transport
Exemptions
None detected

Information requested

My FOI request concerns the two ferries currently being built by Ferguson Marine for Caledonian MacBrayne.

I would like to know when both ferries will be ready to be released for service and how much over budget this now is.

Response

On Monday 26th February, the then Chief Executive Officer of Ferguson Marine (Port Glasgow), Mr David Tydeman, wrote to the Scottish Government's Net Zero, Economy and Transport Committee to provide an update on the two vessels. He stated that the total cost to complete the vessels since the point of public ownership was up to £149.1 million for 801 Glen Sannox and no more than £150 m for 802 Glen Rosa. At the point that Ferguson Marine was taken into public ownership, the forecast future cost for both vessels combined was between £100.1 – 114.3m.

In the same letter, the then Chief Executive stated that the handover dates from FMPG would be 31 May 2024 for 801 and no later than end September 2025 for 802. The deployment of vessels into service after handover is a matter for Caledonian MacBrayne (CalMac).

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

Contact Please quote the FOI reference Central Enquiry Unit Email: ceu@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrews House Regent Road Edinburgh EH1 3DG

Attachments

No attachments found.

Similar releases