202300355920 · FOI · unclear

Figure for the rail enhancement budget in CP6

Published
2023-12-05
Received
2023-05-10
Responded
2023-06-06
Directorate
Topic
Public Sector
Exemptions
None detected

Information requested

The figure for the rail enhancement budget in CP6 at the start of the control period broken down by year and the current enhancement budget for the remainder of CP6 broken down by year.

Response

The budget for the rail regulatory Control Period 6 is to fund the operation, maintenance and renewal of the existing rail infrastructure. Rail enhancements are funded separately and the budgets during the Control Period 6 years are :

2019/20 - £207m

2020/21 - £207m

2021/22 - £173m

2022/23 - £247m

2023/24 – £155.8m

These figures have been published in the Scottish budgets; you might find some helpful information in the links below:

Supporting documents - Scottish Budget: 2023-24 - gov.scot (www.gov.scot)

https://www.gov.scot/binaries/content/documents/govscot/publications/corporate- report/2022/12/scottish-budget-2023-24/documents/scottish-budget-2023-24-level-4-data/scottish-budget-2023-24-level-4-data/govscot%3Adocument/scottish-budget-2023-24-level-4-data.xlsx

Supporting documents - Scottish Budget 2022 to 2023 - gov.scot (www.gov.scot)

Supporting documents - Scottish Budget 2021 to 2022 - gov.scot (www.gov.scot)

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

Contact Please quote the FOI reference Central Enquiry Unit Email: ceu@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrews House Regent Road Edinburgh EH1 3DG