Back to index Original on gov.scot

FOI/202200292153 · FOI · unclear

Deloitte and work undertaken relating to Lochaber project: FOI release

Published
2022-06-22
Received
2022-04-01
Responded
2022-06-10
Directorate
Economic Development Directorate
Topic
Public sector
Exemptions
None detected

Information requested

1) The amount paid to Deloitte for work undertaken relating to the Lochaber guarantee/project to date, broken down by financial year.

2) The amount contracted to be paid in addition to the above that has yet to leave the Scottish Government's accounts.

Response

1. For the first part of your request, the total amount paid to Deloitte for the Lochaber guarantee/project is £1,565,670.40. Below is the total amount broken down by financial year: FY 2017 – £112,251.40 FY 2018 – £180,582.00 FY 2019 – £349,449.60 FY 2020 – £217,601.40 FY 2021 – £705,786.00

2. In addition to the above, some costs had accrued but not yet been settled at the date of the request. This amount was £101,314.00.

About FOI

The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at http://www.gov.scot/foi-responses.

Contact Please quote the FOI reference Central Enquiry Unit Email: ceu@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrews House Regent Road Edinburgh EH1 3DG

Attachments

No attachments found.

Similar releases