FOI/202500475954 · FOI · unclear
A75 and A77 road closure statistics: FOI release
Information requested
You asked for "statistical information about recent closures on the A75 and A77. Would you be able to provide me with the total number of unplanned road closures since 1st January 2025 on the A75 and on the A77 as of the 15th July?"
You also asked "If you could also provide the total number of planned road closures over the same period, that would be helpful as well"
Response
Transport Scotland's Operating Company, Amey confirmed the following planned and unplanned closures on the A75 and A77 trunk roads from 1 January 2025 to 15 July 2025:
Route Planned Closures Unplanned Closures A75 24` 14 A77 47 6
About FOI
The Scottish Government is committed to publishing all information released in response to Freedom of Information requests. View all FOI responses at https://www.gov.scot/foi-responses.
Contact Please quote the FOI reference Central Correspondence Unit Email: contactus@gov.scot Phone: 0300 244 4000 The Scottish Government St Andrew's House Regent Road Edinburgh EH1 3DG
Attachments
No attachments found.